| Actiflo System Rehabilitation
|
Replacement of Lamella Panels and structural supports in ActiFlo Clarification System. Advertise week of 7/22/24.
|
Plant
|
9/25/2024
|
9/25/2026
|
$2,300,000.00
|
|
21% |
33% |
|
| Asbestos Remediation in MPS |
Abatement and disposal of 500 linear feet of abandoned 6-inch steam pipe with asbestos in the MPS basement at the LFWTP. |
Plant
|
1/24/2024
|
7/24/2025
|
$158,525.00
|
|
100% |
100% |
$118,525.00
|
|
Auditorium/Purification Stair Enclosure
|
Rehab of Outside Staircase, HVAC, Lighting
|
Plant |
2/7/2024 |
12/31/2024 |
$1,192,000.00
|
|
100% |
100% |
$954,092.46 |
| Clifton Water Meter Replacement Contract |
Replacement of approximately 4,980 water meters and Radio Frequency Meter Interface Units (RFMIUs) in the City of Clifton. |
Distribution |
6/29/2025 |
730 Days |
$2,006,220.00 |
|
18%
|
21% |
|
| Concrete Restoration within Clifton, Passaic, Lodi, North Arlington and West Milford |
Concrete restoration work following distribution department activities. |
Distribution |
5/6/2024
|
5/5/2026
|
$495,000.00
|
|
On Call |
45% |
|
| Concrete Restoration within Paterson and Prospect Park |
Concrete restoration work following distribution department activities. |
Distribution |
5/6/2024
|
5/5/2026
|
$495,000.00
|
|
On Call |
64% |
|
| Emergency Water Main Repairs
|
Conduct emergency repair services within distribution system.
-CO 1 to make emergency repairs to Kearny multiples for rehab of four (4) pipe crossings with Primus structural liner.
-CO2 to make emergency repairs on transmission mains
|
Distribution |
6/22/2022 |
12/31/2024 |
$7,158,513.00
|
|
100% |
93% |
|
| Emergency Water Main Repairs and Appurtenance Replacement
|
Conduct emergency repair services within distribution system.
|
Distribution |
3/31/2025 |
730 Days |
$8,078,733.00
|
$13,078,733.00 |
73% |
65% |
|
| Filter Building Rehabilitation
|
Replacement of filter influent and drain butterfly valves, replacement of butterfly valves on the washwater piping systems, furnishing and utilization of stop logs for filter isolation, replacement of handrail system within filter rooms, lighting replacement, piping and wall coating system replacements, and concrete repair.
|
Plant |
10/28/2025 |
10/28/2027 |
$7,984,000.00 |
|
1% |
0% |
|
| Great Falls Buildings Rehab
|
Historic rehabilitation of the Gate House and Pump House, two small one-story masonry buildings located in the Paterson Great Falls National Historic Park. |
Plant |
9/1/2023 |
10/1/2024 |
$2,124,400.00 |
|
100% |
100% |
$1,999,266.14 |
| Levine Reservoir Tanks
|
Decommissioning of Levine Reservoir to build 2 new enclosed reservoirs (2.5MG tanks) in its place.
|
Plant |
6/1/2025 |
3/30/2027 |
$41,819,780.00 |
|
10% |
5% |
|
| LFWTP Actiflo Basin Coating
|
Installation of protective coating system on walls, floors, and underside of slab of influent basins, Coagulation basins, Injection Chambers, Flocculation basins, Sedimentation basins, and underside of walkway slabs. |
Plant |
6/30/2025 |
640 Days |
$2,198,185.00 |
|
25% |
16% |
|
| LFWTP Roof Rehabilitation
|
This contract will perform repair/replacement of various roofs in addition to miscellaneous architectural repairs at various locations at the Little Falls Water Treatment Plant. |
Plant |
11/13/2024 |
11/13/2025 |
$1,193,600.00
|
|
90% |
35% |
|
| LSLRs following Test Pitting Operations in Main System
|
LSLR Program for Main System
|
Distribution |
5/11/2022 |
10/31/2025 |
$29,526,085.00 |
|
100% |
97% |
|
| Paterson Water Meter Replacement Contract |
Replacement of approximately 6,640 water meters and Radio Frequency Meter Interface Units (RFMIUs) in the City of Paterson. |
Distribution |
7/11/2025 |
730 Days |
$2,970,394.31 |
|
15% |
45% |
|
|
Replacement of Hydrants
|
Perform replacement of hydrants throughout the distribution system.
|
Distribution |
7/27/2022 |
12/31/2024 |
$11,535,460.00 |
|
100% |
100% |
$11,068,225.87
|
| Residuals Handling Facility |
Construction of new Residuals facility at LFWTP and demolition of existing residuals facility and old filter press building. |
Plant |
7/29/2025 |
960 Days |
$31,189,000.00 |
|
3% |
3%
|
|
| Roadway Pavement Restoration |
Perform roadway pavement restoration following routine maintenance and emergency repairs performed by PVWC Operations. |
Distribution |
9/27/2023 |
10/18/2026 |
$4,499,300.00
|
$6,748,950.00 |
On Call |
47% |
|
| Water Main Replacement and Distribution Projects - Clifton & Passaic |
On-call replacement of up to 20,500 LF of distribution water mains located within the Cities of Clifton, Passaic and other municipalities within the Commission's service area, as needed.
|
Distribution |
11/25/2025 |
11/25/2027 |
$9,298,000.00 |
|
0% |
0% |
|
| Water Main Replacement and Distribution Projects - Paterson & Prospect Park
|
On-call replacement of up to 16,500 LF of distribution water mains located within the Cities of Paterson, Prospect Park and other municipalities within the Commission's service area, as needed.
|
Distribution |
11/25/2025 |
11/25/2027 |
$8,927,505.00 |
|
0% |
0% |
|
| Water Transmission Main Improvement to the Industrial Loop - Advanced Work to Levine Tanks Contract |
Advanced work to the construction of the Levine Tanks for Replacing Transmission Main Valves, Installation of Interconnection between 300/180 Gradients, Structural Liner of Inlet Line to Reservoir, Pressure Relief.
-Five Change Orders as of 7/23/2025
|
Distribution |
5/11/2022 |
11/31/2025 |
$6,752,875.00 |
|
100% |
100% |
$4,321,840.00 |