Replacement of Hydrants
|
Perform replacement of hydrants throughout the distribution system.
|
Distribution |
7/27/2022 |
12/31/2024 |
$11,535,460.00 |
100% |
100% |
$11,068,225.87
|
| Water Transmission Main Improvement to the Industrial Loop - Advanced Work to Levine Tanks Contract |
Advanced work to the construction of the Levine Tanks for Replacing Transmission Main Valves, Installation of Interconnection between 300/180 Gradients, Structural Liner of Inlet Line to Reservoir, Pressure Relief.
-Five Change Orders as of 7/23/2025
|
Distribution |
5/11/2022 |
11/31/2025 |
$6,752,875.00 |
67% |
64% |
|
| LSLRs following Test Pitting Operations in Main System |
LSLR Program for Main System |
Distribution |
5/11/2022 |
10/31/2025 |
$29,526,085.00 |
95% |
87% |
|
| Emergency Water Main Repairs |
Conduct emergency repair services within distribution system.
-CO 1 to make emergency repairs to Kearny multiples for rehab of four (4) pipe crossings with Primus structural liner.
-CO2 to make emergency repairs on transmission mains
|
Distribution |
6/22/2022 |
12/31/2024 |
$7,158,513.00 |
100% |
91% |
|
| Roadway Pavement Restoration |
Perform roadway pavement restoration following routine maintenance and emergency repairs performed by PVWC Operations. |
Distribution |
9/27/2023 |
10/18/2026 |
$4,499,300.00 |
On Call |
63% |
|
| Auditorium/Purification Stair Enclosure |
Rehab of Outside Staircase, HVAC, Lighting |
Plant |
2/7/2024 |
12/31/2024 |
$1,192,000.00 |
100% |
98% |
|
| Concrete Restoration within Clifton, Passaic, Lodi, North Arlington and West Milford |
Concrete restoration work following distribution department activities. |
Distribution |
5/6/2024 |
5/5/2026 |
$495,000.00 |
On Call |
45% |
|
| Concrete Restoration within Paterson and Prospect Park |
Concrete restoration work following distribution department activities. |
Distribution |
5/6/2024 |
5/5/2026 |
$495,000.00 |
On Call |
64% |
|
| LFWTP Roof Rehabilitation |
This contract will perform repair/replacement of various roofs in addition to miscellaneous architectural repairs at various locations at the Little Falls Water Treatment Plant. |
Plant |
11/13/2024 |
11/13/2025 |
$1,193,600.00 |
80% |
35% |
|
| Actiflo System Rehabilitation |
Replacement of Lamella Panels and structural supports in ActiFlo Clarification System. Adverise week of 7/22/24. |
Plant |
9/25/2024 |
9/25/2026 |
$2,300,000.00 |
10% |
23% |
|
| Levine Reservoir Tanks |
Decommissioning of Levine Reservoir to build 2 new enclosed reservoirs (2.5MG tanks) in its place. |
Plant |
6/1/2025 |
3/30/2027 |
$41,819,780.00 |
5% |
1% |
|
| Great Falls Buildings Rehab |
Historic rehabilitation of the Gate House and Pump House, two small one-story masonry buildings located in the Paterson Great Falls National Historic Park. |
Plant |
9/1/2023 |
10/1/2024 |
$2,124,400.00 |
100% |
91% |
|
| Asbestos Remediation in MPS |
Abatement and disposal of 500 linear feet of abandoned 6-inch steam pipe with asbestos in the MPS basement at the LFWTP. |
Plant |
1/24/2024 |
7/24/2025 |
$158,525.00 |
100% |
100% |
$118,525.00 |
| Residuals Handling Facility |
Construction of new Residuals facility at LFWTP and demolition of existing residuals facility and old filter press building. |
Plant |
7/29/2025 |
960 Days |
$31,189,000.00 |
2% |
0% |
|
| LFWTP Actiflo Basin Coating |
Installation of protective coating system on walls, floors, and underside of slab of influent basins, Coagulation basins, Injection Chambers, Flocculation basins, Sedimentation basins, and underside of walkway slabs. |
Plant |
6/30/2025 |
640 Days |
$2,198,185.00 |
10% |
0% |
|
| Emergency Water Main Repairs and Appurtenance Replacement |
Conduct emergency repair services within distribution system. |
Distribution |
3/31/2025 |
730 Days |
$8,078,733.00 |
100% |
4% |
|
| Paterson Water Meter Replacement Contract |
Replacement of approximately 6,640 water meters and Radio Frequency Meter Interface Units (RFMIUs) in the City of Paterson. |
Distribution |
7/11/2025 |
730 Days |
$2,970,394.31 |
10% |
43% |
|
| Clifton Water Meter Replacement Contract |
Replacement of approximately 4,980 water meters and Radio Frequency Meter Interface Units (RFMIUs) in the City of Clifton. |
Distribution |
6/29/2025 |
730 Days |
$2,006,220.00 |
10% |
19% |
|
| Water Main Replacement and Distribution Projects - Clifton & Passaic |
On-call replacement of up to 20,500 LF of distribution water mains located within the Cities of Clifton, Passaic and other municipalities within the Commission's service area, as needed. |
Distribution |
11/25/2025 |
11/25/2027 |
$9,298,000.00 |
0% |
0% |
|
| Water Main Replacement and Distribution Projects - Paterson & Prospect Park |
On-call replacement of up to 16,500 LF of distribution water mains located within the Cities of Paterson, Prospect Park and other municipalities within the Commission's service area, as needed. |
Distribution |
11/25/2025 |
11/25/2027 |
$8,927,505.00 |
0% |
0% |
|